Procedures and Criteria for Installing a New Septic System
- The Site Evaluation application form must be completely filled out, signed by the owner or legally authorized representative, and submitted to the appropriate office along with the fee. A tax lot map, a detailed drawing of the proposed development, and directions to the property must be included. You must also provide at least 2 test pits at least 75 feet apart (more are necessary for large systems) in the proposed drainfield area. The specific requirements for test pits are provided with the Site Evaluation information packet.
- After a completed application is received, an Onsite Specialist will visit your property to perform the Site Evaluation. Depending on weather, test pit placement and if additional test pits need to be dug, more than one visit may be necessary. Our goal is to respond to completed Site Evaluation applications within three (3) weeks of receiving them however during the summer it may take up to 5 weeks.
- You will receive a Site Evaluation Report that specifies the approved area, the type and size of the septic system required and any special requirements. Should the site be rejected, you have 90 days in which you may provide additional test pits for evaluation with no additional fees. The Site Evaluation Report will also give you information such as applying for a site evaluation report review and the opportunity to apply for a variance from any rule or standard.
- To prevent a delay, fully complete the application, including the owner’s or legally authorized representative’s signature, and submit it along with the required fees. At a minimum, the following documents must be attached:
- A copy of the Site Evaluation Report.
- A Land Use Compatibility Statement signed by your county’s land use agency.
- A vicinity/locator map.
- A detailed Site Development Plan and directions to the property.
- Detailed plans and specifications for the installation of the system. For Construction-Installation permitted systems, the plans must be drawn by the property owner or a DEQ-licensed installer.
- A Construction-Installation Permit will be issued within 20 days of receiving a completed application. Once you have the permit in hand, you may proceed with the installation of the septic system prescribed in the permit. Any changes must receive approval from the onsite agent for your county. Note: A septic system must be installed and constructed by the owner or a DEQ-licensed installer using DEQ-approved materials and equipment that meet minimum standards. All equipment must be installed and operated according to the manufacturer’s specifications. If you have questions about installers or approved materials and equipment the Environmental Health Office.
- A "pre-cover" inspection (before it is covered with soil) of the installation is required unless waived by the onsite agent for your county. Some complex systems, such as sandfilter systems, require inspections at various stages of construction and these inspection requirements are specified in the permit.
To initiate the pre-cover inspection the installer must complete the As-Built Drawing and Materials List form (included in the permit packet) and submit it to your county’s onsite agent. This form must be signed by the installer certifying that it was installed according to DEQ specifications. Within seven (7) days of receipt of this completed form, the onsite agent for your county will either waive or conduct the inspection.
After completion of a satisfactory inspection you may cover the installation. You will be sent a Certificate of Satisfactory Completion (CSC) in the mail. Upon receipt of the CSC, you may begin using the septic system.